Solar PV G99 up to 50kW Application
For larger or more complex renewable energy systems, a G99 application must be submitted to the Distribution Network Operator (DNO) before installation. This approval process ensures the system integrates safely with the local electricity network and does not disrupt grid stability.
What is a G99 Application?
The G99 standard applies to renewable energy installations that exceed the limits set by G98.
This typically includes:
Single-phase systems over 16A per phase (≈3.68kW)
Three-phase systems over 11kW
Larger commercial or industrial renewable installations
Battery storage systems exporting significant power
Unlike G98, a G99 application requires DNO approval before installation.
What’s Required for a G99 Application?
Installer & Customer Details:
Company name & accreditation (e.g., MCS certification)
Installer and customer contact details
Site address
System & Connection Details:
Type of renewable system (Solar PV, battery storage, heat pump, etc.)
Total generation capacity (kW)
Inverter manufacturer, model, and G99 compliance certificate
Connection type (e.g., single-phase or three-phase)
Export limitation details (if applicable)
Technical Documentation:
Single-Line Diagram (SLD) – showing how the system connects to the grid
Protection settings (voltage/frequency trip settings, anti-islanding details)
Fault level contribution data (impact of the system on the grid)
Site layout plans (where the equipment is installed)
DNO application form (specific to the network operator)
Application Submission & Fees:
The application must be submitted before installation begins
A G99 application fee is required (varies by DNO)
The DNO reviews the application, which may take 45-60 days
What Happens Next?
The DNO will assess the application and:
Approve the connection with or without conditions
Request modifications or network reinforcement (if needed)
Once approved, installation can proceed, and a G99 commissioning report must be submitted post-installation.
At Grid Guru, we manage the entire G99 application process from paperwork to technical documentation, ensuring a smooth and compliant approval process.
Need help with your G99 application? Contact us today!