Solar PV G99 Applications 50kW - 1MW Application
For large-scale renewable energy systems above 50kW, a more detailed G99 application must be submitted before installation to the Distribution Network Operator (DNO). This ensures the system integrates safely with the grid, as larger systems can have a significant impact on network stability.
What is a G99 Application for Systems Above 50kW?
The G99 standard applies to larger renewable energy installations exceeding:
50kW three-phase
Commercial, industrial, and large-scale generation
Large battery storage and hybrid systems
These applications require a more in-depth assessment due to their potential effect on the electricity grid.
What’s Required for a G99 Application Above 50kW?
Company name & accreditation (e.g., MCS, NICEIC certification)
Installer and customer contact details
Site address
System & Connection Details:
Type of renewable system (Solar PV, wind, battery storage, CHP, etc.)
Total generation capacity (kW/MW)
Inverter manufacturer, model, and G99 compliance certificate
Connection type (e.g., LV or HV, single or three-phase)
Expected export capacity and any agreed constraints
Technical Documentation:
Single-Line Diagram (SLD) – detailed connection diagram
Protection settings (voltage/frequency trip settings, anti-islanding, G99 relay details)
Fault level contribution data (how the system impacts the grid)
Power quality study (if required by the DNO)
Earthing & harmonic impact assessment
DNO application form (specific to the network operator)
Application Submission & Fees:
G99 applications over 50kW require more extensive review
A G99 application fee applies (varies by DNO)
The DNO review process typically takes 60-90 days
Grid reinforcement may be required, depending on local capacity
What Happens Next?
The DNO will assess the application and:
Approve the connection with or without conditions
Request grid upgrades or reinforcement before approval
Once approved, installation can proceed, and a G99 commissioning report must be submitted post-installation.
At Grid Guru, we handle the entire G99 application process for large-scale renewable systems, ensuring all technical requirements and paperwork are completed for a smooth grid approval.
Need expert help with your G99 application? Contact us today!
POWERFUL SOLUTIONS
Get in Touch with Us
Please use the form or contact details below to get in touch with us. We look forward to speaking with you, discuss ideas, and look at ways we can support your next project.